A supply and commissioning agreement between Harbourline Power Pty Ltd (the Principal) and Calder Transformer Services (the Provider)
- Parties
- Calder Transformer Services and Harbourline Power Pty Ltd
- Engagement value
- AUD 1,180,000
- Completion
- End of week 36
- Payment timing
- payable 30 days from the response
What matters
Six milestone payments totalling AUD 1,180,000, from design to handover.
Commissioning is due by the end of week 36. Late completion attracts liquidated damages of AUD 4,200 per day. Clause 4.7 sets the date and clause 9.2 supplies the rate.
Schedule 1 refers to the outage window for energisation but does not state its dates. The window requires confirmation.
Review the obligations
Calder Transformer Services shall complete commissioning by the end of week 36; late completion attracts liquidated damages of AUD 4,200 per day under clause 9.2.
clause 4.7Calder Transformer Services must deliver the transformer to site in week 30; risk passes to the Principal on delivery under clause 2.6.
clause 2.3Harbourline Power Pty Ltd must respond to each claim within 10 business days, with the reasons recorded.
clause 6.2Harbourline Power Pty Ltd must pay the responded amount of each claim.
clause 6.4Review the payment schedule
AUD 1,180,000GST excluded, six milestones
M1Design and shop drawings
AUD 120,000
M2Factory acceptance test
AUD 180,000
M3Delivery to site (week 30)
AUD 380,000
M4Installation and connection
AUD 200,000
M5Commissioning and energisation (week 36)
AUD 220,000
M6As-built records and handover
AUD 80,000
Calder Transformer Services is engaged as the provider to supply, deliver and commission the transformer, under a fixed-fee agreement of AUD 1,180,000 paid across six milestones from design to handover.
A fixed-fee supply and commissioning agreement. Each milestone is a discrete deliverable carrying its own payment, claimed against the Payment Schedule and payable 30 days from the response. The transformer must reach site in week 30 and commissioning must be complete by the end of week 36, with liquidated damages of AUD 4,200 per day for delay.
Calder Transformer Services shall complete commissioning by the end of week 36; late completion attracts liquidated damages of AUD 4,200 per day under clause 9.2.
clause 4.7Calder Transformer Services must deliver the transformer to site in week 30; risk passes to the Principal on delivery under clause 2.6.
clause 2.3Harbourline Power Pty Ltd must respond to each claim within 10 business days, with the reasons recorded.
clause 6.2Harbourline Power Pty Ltd must pay the responded amount of each claim.
clause 6.4The money
AUD 1,180,000GST excluded, six milestones
M1Design and shop drawings
AUD 120,000
M2Factory acceptance test
AUD 180,000
M3Delivery to site (week 30)
AUD 380,000
M4Installation and connection
AUD 200,000
M5Commissioning and energisation (week 36)
AUD 220,000
M6As-built records and handover
AUD 80,000
What matters
Six milestone payments totalling AUD 1,180,000, from design to handover.
Commissioning is due by the end of week 36. Late completion attracts liquidated damages of AUD 4,200 per day. Clause 4.7 sets the date and clause 9.2 supplies the rate.
Schedule 1 refers to the outage window for energisation but does not state its dates. The window requires confirmation.